Please be informed that there will be power service interruption as indicated in the schedule/s below:
Scheduled Power Interruption
Date & Time | Affected Areas | Reason |
June 22 (MONDAY) 9:00AM – 1:00PM | Purok 9, Maputi, Naawan | To facilitate replacement of rotten pole |
June 23 (TUESDAY) 9:00AM – 1:00PM | •Portion of Poblacion, Lugait (Sitio Tigbao-o) •Entire Lower Talacogon •Upper Talacogon •Kaluknayan •Aya-aya •Betahon •Lugait •Entire Sitio Danao Cabalantian •Purok 5, Upper Suminanap •Pagawan, Manticao •Entire Hindang, Iligan City | To facilitate replacement of rotten pole |
June 24 (WEDNESDAY) 9:00AM – 1:00PM | NAAWAN DISTRICT •Entire Purok 2 and Purok 5 Maputi •Entire Tuburan | To facilitate relocation of pole |
June 25 (THURSDAY) 9:00AM – 1:00PM | NAAWAN DISTRICT •Portion of Purok 2, Patag •Purok 7, Mapulog •Entire Purok 4, 5, and 6, Patag •Tagbalogo •Mat-I •Lubilian | To facilitate relocation of pole due to road widening |
June 25 (THURSDAY) 9:00AM – 12:00NN | • Building A, B, and C Familia Apartment • Bamboo Lane | To facilitate removal of pole and stringing of 3-phase line |
June 25 (THURSDAY) 2:00PM – 5:00PM | Portion of Purok 2 Tigkawayan, Sinaloc, El Salvador | To facilitate transformer management – replacement of 2 units of transformer |
June 26 (FRIDAY) 9:00AM – 2:00PM | Portion of D-2 Canitoan (Along Flores Eatery, Pryce Gas, and Botoy’s Storage) | To facilitate re-structuring of the 3-phase line |
Power will be restored once the activity is completely executed and not necessarily following the above-stated schedule.