Please be informed that there will be power service interruption as indicated in the schedule/s below:
Scheduled Power Interruption
Date & Time | Affected Areas | Reason |
SEPTEMBER 7, 2020 (MONDAY) 08:00AM – 12:00NN | LAGUINDINGAN DISTRICT • Entire Purok 2 Liberty | To facilitate cutting of trees |
SEPTEMBER 8, 2020 (TUESDAY) 09:00AM – 01:00PM | MANTICAO DISTRICT • Entire Pagawan | To facilitate installation of mid-pole due to obstruction of the on-going construction of Barangay Arc |
SEPTEMBER 9, 2020 (WEDNESDAY) 08:00AM – 05:00PM | OPOL DISTRICT • Entire BGS and Nakulian, Bagocboc | To facilitate conversion of line and line clearing |
SEPTEMBER 10, 2020 (THURSDAY) 08:00AM – 05:00PM | LAGUINDINGAN DISTRICT • Portion of Purok 3 and 5 Lapad GITAGUM DISTRICT • Entire Purok 8 Sikiton, G Pelaez | To facilitate preventive maintenance |
Power will be restored once the activity is completely executed and not necessarily following the above-stated schedule.