Please be informed that there will be power service interruption as indicated in the schedule/s below:
Scheduled Power Interruption
Date & Time | Affected Areas | Reason |
August 15, 2020 (SATURDAY) 7:00AM – 8:00AM and 3:00PM – 4:00PM | EL SALVADOR DISTRICT • Portion of Sinaloc, Megasoft & Monark ALUBIJID DISTRICT • Portion of Lanao, Molocboloc, Baybay, Entire Poblacion, Loguilo & Lagtang LAGUINDINGAN DISTRICT • Portion of Moog GITAGUM DISTRICT • Portion Burnay, Entire Matangad, Pangayawan, CP Garcia, Ulab, G Pelaez, Quezon & Kilangit LIBERTAD DISTRICT • All Barangays INITAO DISTRICT • Lasang Forest Adventure Park | To facilitate switching activity |
August 15, 2020 (SATURDAY) 07:00AM – 09:00AM and 03:00PM – 04:00PM | ALUBIJID DISTRICT • Portion of Lumbo, Entire Benigwayan, Lourdes, Taparak, Sungay & Tula LAGUINDINGAN DISTRICT • Portion of Sinai, Entire Poblacion, Lapad, Aromahon, Gasi & CAAP Airport | To facilitate preventive maintenance of Lumbo S/S Equipment |
August 15, 2020 (SATURDAY) 07:00AM – 04:00PM | LAGUINDINGAN DISTRICT • P-5 Sinai & P-4 Liberty,P1-5 & P7-8 Kibaghot, Sambulawan, Mauswagon & Tubajon GITAGUM DISTRICT • Portion of Burnay, Entire Poblacion, Cogon & Tala-o | To facilitate preventive maintenance of Moog S/S Equipment, interconnection of 3-Phase lines and replacement of insulators and rotten poles. |
August 18, 2020 (TUESDAY) 8:00AM – 11:00AM | INITAO DISTRICT • Portion of Purok 1 San Pedro | To facilitate replacement of overloaded transformer |
August 18, 2020 (TUESDAY) 9:00AM – 1:00PM | INITAO DISTRICT • Portion of Purok 5, Entire Purok 6 Puting Bato, Purok 7 Lulang, Tawan-tawan | To facilitate replacement of buckled pole |
August 18, 2020 (TUESDAY) 1:00PM – 2:00PM | INITAO DISTRICT • Bliss San Pedro | To facilitate transformer management |
August 22, 2020 (SATURDAY) 10:00AM – 2:00PM | MANTICAO DISTRICT • Portion of Donque Hills, Upper Malubog | To facilitate replacement of rotten pole |
Power will be restored once the activity is completely executed and not necessarily following the above-stated schedule.