Please be informed that there will be power service interruption as indicated in the schedule/s below:

Scheduled Power Interruption

Date & TimeAffected AreasReason
August 15, 2020 (SATURDAY) 7:00AM – 8:00AM and 3:00PM – 4:00PMEL SALVADOR DISTRICT
• Portion of Sinaloc, Megasoft & Monark

ALUBIJID DISTRICT
• Portion of Lanao, Molocboloc, Baybay, Entire Poblacion, Loguilo & Lagtang

LAGUINDINGAN DISTRICT
• Portion of Moog

GITAGUM DISTRICT
• Portion Burnay, Entire Matangad, Pangayawan, CP Garcia, Ulab, G Pelaez, Quezon & Kilangit

LIBERTAD DISTRICT
• All Barangays

INITAO DISTRICT
• Lasang Forest Adventure Park
To facilitate switching activity
August 15, 2020 (SATURDAY) 07:00AM – 09:00AM and 03:00PM – 04:00PMALUBIJID DISTRICT
• Portion of Lumbo, Entire Benigwayan, Lourdes, Taparak, Sungay & Tula

LAGUINDINGAN DISTRICT
• Portion of Sinai, Entire Poblacion, Lapad, Aromahon, Gasi & CAAP Airport
To facilitate preventive maintenance of Lumbo S/S Equipment
August 15, 2020 (SATURDAY) 07:00AM – 04:00PMLAGUINDINGAN DISTRICT
• P-5 Sinai & P-4 Liberty,P1-5 & P7-8 Kibaghot, Sambulawan, Mauswagon & Tubajon

GITAGUM DISTRICT
• Portion of Burnay, Entire Poblacion, Cogon & Tala-o
To facilitate preventive maintenance of Moog S/S Equipment, interconnection of 3-Phase lines and replacement of insulators and rotten poles.
August 18, 2020 (TUESDAY) 8:00AM – 11:00AMINITAO DISTRICT
• Portion of Purok 1 San Pedro
To facilitate replacement of overloaded transformer
August 18, 2020 (TUESDAY) 9:00AM – 1:00PMINITAO DISTRICT
• Portion of Purok 5, Entire Purok 6 Puting Bato, Purok 7 Lulang, Tawan-tawan
To facilitate replacement of buckled pole
August 18, 2020 (TUESDAY) 1:00PM – 2:00PMINITAO DISTRICT
• Bliss San Pedro
To facilitate transformer management
August 22, 2020 (SATURDAY) 10:00AM – 2:00PMMANTICAO DISTRICT
• Portion of Donque Hills, Upper Malubog
To facilitate replacement of rotten pole

Power will be restored once the activity is completely executed and not necessarily following the above-stated schedule.