Please be informed that there will be power service interruption as indicated in the schedule/s below:

Schedule Power Interruption

Date & TimeAffected AreasReason
08:00AM – 11:00AM



LAGUINDINGAN DISTRICT
• Entire Poblacion
• Bolobolo URC
• Divine Mercy
• Donau Carbon
To facilitate the relocation of poles affected by DPWH road widening
8:00AM – 5:00PM• Portion of Sinaloc
• Portion of Poblacion
To facilitate the relocation of poles affected by DPWH road widening
9:00AM – 12:00NN• Sitio Hawaii
• Sitio Kiam-is
• Sitio Tagbocboc
• Sitio Maalong-along
To facilitate cutting of 10 Falcatta trees along our single phase line

Power will be restored once the activity is completely executed and not necessarily following the above-stated schedule.